Construction of a small hydroelectric power plant (HPP) with an installed capacity of 0.5 MW at the Hydroelectric complex on the Kusak River
Construction of a small hydroelectric power plant (HPP) with an installed capacity of 0.5 MW at the Hydroelectric complex on the Kusak River
The project provides for the construction of a small hydroelectric power plant (HPP) with an installed capacity of 0.5 MW at the Kusak River hydroelectric complex in the Urzhar district of the Abay region. The maximum power generation capacity is 1,800,000 kWh.
- Indicator Results
- Investment amount, thousand US dollars 1 133
- NPV of the Project thousand, US dollars 460
- IRR, % 19
- EBITDA yield, %
- Payback period, years 12
- Discounted payback period, years - - 15,3